6 men can do a piece of work in 12 days while 8 women can do the same work in 18 days. The same work can be done by 18 children in 10 days. 4 men, 12 women and 20 children work together for 2 days. If only men have to complete remaining work in 1 day, then find the required number of men.
Correct Answer: Description for Correct answer:
\( \Large 6\times 12 \) men = \( \Large 8\times 18 \) women
= \( \Large 18\times 10 \) children
=> 12 men = 24 women = 30 children
=> 2 men = 4 women = 5 children
Now, 4 men + 12 women + 20 children
=4 men + 6 men + 8 men = 18 men
Time to do remaining work for 1 man
= \( \Large 16\times 12-18\times 2 \)=36 days
Required number of men to finish the work in 1 day = 36