A can build up a structure in 8 days and B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the structure ?


A) 10 days

B) 9 days

C) 12 days

D) \( \Large 7\frac{1}{3} \)days

Correct Answer:
D) \( \Large 7\frac{1}{3} \)days

Description for Correct answer:

A's 1 day's work = 1/8

B's 1 day's work in breaking the building

= 1/3

Now, according to the question,

A's 4 day's work = \( \Large 4\times 1/8=\frac{1}{2} \)

Now, A's and B's 2 day's work

=\( \Large 2\left(\frac{1}{8}-\frac{1}{3}\right) \)=\( \Large 2\times -5/24=\frac{-10}{24} \)

Total work done in 6 days

\( \Large \frac{1}{2} \)+\( \Large \left(\frac{-10}{24}\right) \)=\( \Large \frac{12-10}{24}=\frac{1}{12} \)

Remaing work = \( \Large 1-\frac{1}{12}=\frac{11}{12} \)

Now, A has to complete the work, so A can complete in x days.

\( \Large \frac{1}{8}\times x=\frac{11}{12} \)=> x=\( \Large \frac{11\times 8}{12} \)

x=\( \Large \frac{11\times 2}{3} \)=\( \Large  7\frac{1}{3} \)days.


Part of solved Time and work questions and answers : >> Aptitude >> Time and work








Comments

No comments available




Similar Questions
1). 6 men can do a piece of work in 12 days while 8 women can do the same work in 18 days. The same work can be done by 18 children in 10 days. 4 men, 12 women and 20 children work together for 2 days. If only men have to complete remaining work in 1 day, then find the required number of men.
A). 36
B). 24
C). 18
D). Couldn't be determined
-- View Answer
2). A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days. In how many days can C working alone complete the work ?
A). 12
B). 68
C). 72
D). 90
-- View Answer
3). A and B each working alone can do a work in 15 days and 25 days, respectively. They started the work together but B left after some time and A finished the remaining work in 7 days. After how many days from the start did B leave ?
A). 3
B). 5
C). 7
D). 9
-- View Answer
4). Consider the following diagrams x men, working at constant speed, do a certain job in y days. Which one of these diagrams shows the relation between x and y?
A). Diagram I
B). Diagram II
C). Diagram III
D). Diagram IV
-- View Answer
5). A, B and C can do a piece of work individually in 8, 12 and 15 days, respectively. A and B start working but A quits after working for 2 days. After this, C joins B till the completion of work. In how many days will the work be completed?
A). \( \Large 5\frac{8}{9} \)days
B). \( \Large 4\frac{6}{7} \)days
C). \( \Large 6\frac{7}{13} \)days
D). \( \Large 3\frac{3}{4} \)days
-- View Answer


6). Ramu wanted to borrow Rs.1000 from a moneylender for a period of one year. However, the moneylender deducted Rs.200 as interest charges and gave Rs.800 to Ramu. Ramu returned Rs.1000 at the end of the year. The rate of interest charged by the moneylender is
A). 20%
B). 22.50%
C). 25%
D). 27.50%
-- View Answer
7). Rajan borrowed Rs.50000 from Rakesh at simple interest. After 3 years, Rakesh got Rs.3000 more than what he had given to Rajan. What was the rate of interest per annum?
A). 2%
B). 5%
C). 8%
D). 10%
-- View Answer
8). Rakesh took a loan for 7 years at the rate of 6 % p.a. S.I. If total interest paid was Rs.2100, then principal was
A). Rs.4400
B). Rs.4800
C). Rs.5000
D). Rs.5200
-- View Answer
9). How much should money lender lend at simple rate of interest of 15% in order to have Rs.3234 at the end of \( \Large 1\frac{1}{2} \) years?
A). Rs.1640
B). Rs.2620
C). Rs.2610
D). Rs.2640
-- View Answer
10). If an amount Rs.8000 becomes to Rs.9200 in 3 years at simple interest. If rate of interest is increased by 3%, it would amount to
A). Rs.9920
B). Rs.10560
C). Rs.11120
D). Rs.11820
-- View Answer