A) 10 days |
B) 9 days |
C) 12 days |
D) \( \Large 7\frac{1}{3} \)days |
D) \( \Large 7\frac{1}{3} \)days |
A's 1 day's work = 1/8
B's 1 day's work in breaking the building
= 1/3
Now, according to the question,
A's 4 day's work = \( \Large 4\times 1/8=\frac{1}{2} \)
Now, A's and B's 2 day's work
=\( \Large 2\left(\frac{1}{8}-\frac{1}{3}\right) \)=\( \Large 2\times -5/24=\frac{-10}{24} \)
Total work done in 6 days
\( \Large \frac{1}{2} \)+\( \Large \left(\frac{-10}{24}\right) \)=\( \Large \frac{12-10}{24}=\frac{1}{12} \)
Remaing work = \( \Large 1-\frac{1}{12}=\frac{11}{12} \)
Now, A has to complete the work, so A can complete in x days.
\( \Large \frac{1}{8}\times x=\frac{11}{12} \)=> x=\( \Large \frac{11\times 8}{12} \)
x=\( \Large \frac{11\times 2}{3} \)=\( \Large 7\frac{1}{3} \)days.