A) \( \Large 5\frac{8}{9} \)days |
B) \( \Large 4\frac{6}{7} \)days |
C) \( \Large 6\frac{7}{13} \)days |
D) \( \Large 3\frac{3}{4} \)days |
A) \( \Large 5\frac{8}{9} \)days |
Work done by A and B in 1 day
=\( \Large \frac{1}{8}+\frac{1}{12}=\frac{5}{24} \)
2 day's work of A and B = \( \Large \frac{10}{24} \)
After 2 day's A left the work
Remaining work = \( \Large 1-\frac{10}{24}=\frac{14}{24} \)
One day work of B and C together
= \( \Large \frac{1}{12}+\frac{1}{15}=\frac{9}{60} \)
So, the number of days required by B and C to finish work
= \( \Large \frac{14/24}{9/60} \)=\( \Large \frac{14}{24}\times {60}{9}=\frac{35}{9} \)
Total days to complete the work
= \( \Large 2+\frac{35}{9}=\frac{53}{9} \)=\( \Large 5\frac{8}{9} \) days.