A) 15 days |
B) 18 days |
C) 20 days |
D) 25 days |
C) 20 days |
(A + B)'s 1 day's work = 1/12
B's 1 day's work = 1 /30
A's 1 day's work = \( \Large\frac {1}{12}- \frac{1}{30} = \frac{5-2}{60} = \frac{1}{20}\)
A alone can finish the work in 20 days.