A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in
A) 8 days
B) 7 days
C) 7(2/3) days
D) 6 days
Correct Answer:
A) 8 days
Description for Correct answer:
Let the required days be x.
A works for (x - 2) days, while B works for x days.