A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is


A) 16

B) 32

C) 64

D) 128

Correct Answer:
C) 64

Description for Correct answer:

Let B will take x days to complete the remaining job.

According to the question,

\( \Large\frac{1}{A} + \frac{1}{B} = \frac{1}{24} \  and  \  \frac{1}{A} = \frac{1}{32}\)

\( \Large\frac{1}{B} = \frac{1}{24} - \frac{1}{32} = \frac{1}{96} \)

= > B = 96 days

According to the question,

\( \Large8 \times \left( \frac{1}{A} + \frac{1}{B}\right) + x \times \frac{1}{B}=1\)

\( \Large 8 \times \frac{1}{24}+ \frac{x}{96}= 1 \)

\( \Large\frac{1}{3} + \frac{x}{96} = 1 \)

\( \Large\frac{x}{96} = 1 - \frac{1}{3} \)

\( \Large x = \frac{2 \times 96}{3} = 64 \)

Hence, B completes the remaining job in 64 days.


Part of solved Time and work questions and answers : >> Aptitude >> Time and work








Comments

No comments available




Similar Questions
1). Ajay can do a piece of work in 25 days and Sanjay can finish it in 20 days. They work together for 5 days and then Ajay goes away. In how many days will Sanjay finish the remaining work?
A). 11 days
B). 14 days
C). 12 days
D). None of these
-- View Answer
2). 10 men can make a wall in 8 days. How many men required to complete the same work in half day ?
A). 80
B). 100
C). 120
D). 160
-- View Answer
3). 6 boys can complete a piece of work in 16 h. In how many hours will 8 boys complete the same work?
A). 10
B). 8
C). 12
D). 14
-- View Answer
4). In a hostel, there are 120 students and food stock is for 45 days. If 30 new students join the hostel, in how many days will the complete stock be exhausted?
A). 38
B). 40
C). 32
D). 36
-- View Answer
5). If 5 boys take 7 h to pack 35 toys, how many boys can pack 65 toys in 3 h?
A). 26
B). 39
C). 45
D). None of the above
-- View Answer


6). 20 women can complete a piece of work in 7 days. If 8 more women are put on the job. In how many days will they complete the work?
A). 4.5 days
B). 5 days
C). 5.5 days
D). 4.5 days
-- View Answer
7). 12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work?
A). 28
B). 36
C). 48
D). 52
-- View Answer
8). 20 men can cut 30 trees in 4 h. If 4 men leave the job, how many trees will be cut in 12 h?

A). 72
B). 80
C). 68
D). 79
-- View Answer
9). 40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day

A). 32
B). 18
C). 36
D). 9
-- View Answer
10). 20 men complete one-third of a work in 20 days. How many more men should be employed to finish the rest of work in 25 more days?
A). 15
B). 12
C). 18
D). 25
-- View Answer