x can copy 80 pages in 20 hours, x and y together can copy 135 pages in 27 hours. Then y can copy 20

pages in


A) 20 hours

B) 24 hours

C) 3 hours

D) 12 hours

Correct Answer:
A) 20 hours

Description for Correct answer:
Rx =\( \Large \frac{80}{20} \) pages/hr

=4 p/h

\( \Large R \left(x+y\right) \frac{135}{27} \) pages/hr

=5 p/h

Ry=\( \Large R \left(x+y\right) -Rx = \left(5-4\right) \)

=1 p/h

y can copy 20 pages =\( \Large \frac{20p}{1p/h} \)

=20 h

Part of solved Time and work questions and answers : >> Aptitude >> Time and work








Comments

No comments available




Similar Questions
1). Work done by \( \Large \left(x+4\right) \) men in \( \Large \left(x+5\right) \) days is equal to the work

done by \( \Large \left(x-5\right) \)men in \( \Large \left(x+20\right) \) days. Then the value of x is
A). 15
B). 20
C). 25
D). 30
-- View Answer
2). Ganga and Saraswati, working separately can plough a field in 8 and 12 hours respectively. If they

work in stretches of one hour alternately. Ganga begins at 9 a.m., when will the ploughing be

completed ?
A). 6 p.m.
B). 6.30 p.m.
C). 5 p. m.
D). 5.30 p.m.
-- View Answer
3). A and B can separately finish a piece of work in 20 days and 15 days respectively. They worked together for 6 days, after which B was replaced by C. If the work was finished in next 4 days, then the number of days in which C alone could do the work is
A). 60 days
B). 40 days
C). 50 days
D). 30 days
-- View Answer
4). If 4 men and 6 women can complete a work in 8 days while 3 men and 7 women can complete it in 10

days, then 10 women complete it in
A). 35 days
B). 50 days
C). 45 days
D). 40 days
-- View Answer
5). A can do a piece of work in 12 days and B in 24 days. If they Work together, in how many days will they

finish the work?
A). 20 days
B). 8 days
C). 12 days
D). 15 days
-- View Answer


6). A, B and C working separately can do a piece of work in 11 days, 20 days and 55 days respectively. In

how many days the work will be completed if A is assisted by B and C on alternate days?
A). 8
B). 4
C). 6
D). 2
-- View Answer
7). Amit, Bhawna and Chandan can do a piece of work, working together in one day only. Amit is 5 times

efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone?
A). 4
B). 5
C). 3
D). \( \Large 2\frac{2}{5} \)
-- View Answer
8). A, B and C can complete a work in 10 days, 20 days and 30 days respectively. They start work together

and work for 4 days. After 4 days, A starts working with double efficiency and C starts working with half

of his efficiency. In how many days work will be completed?
A). 1
B). 4
C). 5
D). 6
-- View Answer
9). 12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how

many days can 5 men and 5 women complete the same work?
A). \( \Large 20\frac{4}{7} \) days
B). \( \Large 2\frac{4}{7} \) days
C). \( \Large 20\frac{3}{7} \) days
D). 18 days
-- View Answer
10). A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days and

remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
A). 10 days
B). 9 days
C). 12 days
D). 15 days
-- View Answer