3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. 4 men and 4 children together will finish the work in how many days?
A) 10
B) 6
C) 12
D) 9
Correct Answer:
D) 9
Description for Correct answer:
3 men = 6 children
1 man = 2 children
4 men + 4 children = 4 men +(4/2)men = 6 men
Given M1 = 3, M2 = 6, D1 = 18 W1 = W2 = 1 and D2 = ?