Ajay's 1 day's work = 1/25
Similarly, Sanjay's 1 day's work = 1/20
Ajay's and Sanjay's together 1 day's work
=\( \Large\frac{1}{25} + \frac{1}{20} = \frac{4 + 5}{100} = \frac{9}{100} \)
Their 5 day's work together = 5 x 1 day's work
=\( \Large 1 - \frac{45}{100} = \frac{55}{100} \)
Now, this remaining work is done by Sanjay.
Let Sanjay takes x days to complete it.
Then, \( \Large\frac{1}{20} \times x = \frac{55}{100} \)
\( \Large\frac{55 \times 20}{100} \)
X = 11 days
So, remaining work is done in 11 days by Sanjay.