3 men can do a piece of work in 18 days. 6 boys can also do the same work in 18 days. In how many days, 4 men and 4 boys together will finish the work?
A) 10 days
B) 6 days
C) 12 days
D) 9 days
Correct answer:
D) 9 days
Description for Correct answer:
3 men = 6 boys
= 1 man = 2 boys
Therefore, 4 man + r boys = 4 mean + 2 men = 6 men
Therefore, 3 men can do a work in 18 days.
Therefore, 1 man can do a work in 18 X 3 days.
Therefore, 6 men can do the work in \( \Large \frac{18 \times 3}{6} \) days
Therefore, Required number of days = \( \Large \frac{2000 \times 20}{25} \) = 9 days
Please provide the error details in above question
Report Error
Recent Activities
General Knowledge
More questions and answers on- General Knowledge
Aptitude
More questions and answers on- Aptitude
Number System
More questions and answers on- Number System
Time and Distance
More questions and answers on- Time and Distance
Average
More questions and answers on- Average
Time and work
More questions and answers on- Time and work
Simple and compound interest
More questions and answers on- Simple and compound interest
Mensuration
More questions and answers on- Mensuration
Number series
More questions and answers on- Number series
Pipes and Cisterns
More questions and answers on- Pipes and Cisterns
Linear Equations
More questions and answers on- Linear Equations
Quadratic Equations
More questions and answers on- Quadratic Equations
Simplification
More questions and answers on- Simplification
Approximation
More questions and answers on- Approximation
Word problems
More questions and answers on- Word problems